• Latest
Karuma Hydropower May not Meet June Deadline- Auditor General

Karuma Hydropower May not Meet June Deadline- Auditor General

4 years ago
Archbishop His Grace Rev. Dr Kaziimba Pledges to Champion & Popularize Census

Kaziimba: Appointment of New Canterbury Archbishop Deepens Anglican Rift

10 hours ago
Gen Otafiire Urges African Unity, Calls Divisionism Greatest Existential Threat

Otafiire to Hand Over Pan-African Movement Chairmanship After 31 Years

18 hours ago
CPA Ben Patrick Kagoro Honoured with ICPAU Gold Service Award

CPA Ben Patrick Kagoro Honoured with ICPAU Gold Service Award

19 hours ago
Gloria Tuhaise Wakooba Named CPA of the Year 2025

Gloria Tuhaise Wakooba Named CPA of the Year 2025

19 hours ago
Uganda Courts Mauritian Travellers at Inaugural Tourism Roadshow

Uganda Courts Mauritian Travellers at Inaugural Tourism Roadshow

20 hours ago
UPC’s Ogwal Backs Museveni in Kwania Amid Calls for Development

UPC’s Ogwal Backs Museveni in Kwania Amid Calls for Development

20 hours ago
SoftPower News
Sunday, October 5, 2025
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
    • Fashion
  • Regional
    • Kenya
    • Rwanda
    • Tanzania
    • Burundi
    • South Sudan
    • DR Congo
  • Defence & Security
  • Sport
  • Entertainment
  • More
    • Agriculture
    • Africa
    • Columnists
    • Education
    • Health
      • COVID-19
    • International News
    • News in Pictures
    • OpEd
    • Pearl Of Africa
    • People
    • Politics
    • Special Reports
    • Women
No Result
View All Result
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
    • Fashion
  • Regional
    • Kenya
    • Rwanda
    • Tanzania
    • Burundi
    • South Sudan
    • DR Congo
  • Defence & Security
  • Sport
  • Entertainment
  • More
    • Agriculture
    • Africa
    • Columnists
    • Education
    • Health
      • COVID-19
    • International News
    • News in Pictures
    • OpEd
    • Pearl Of Africa
    • People
    • Politics
    • Special Reports
    • Women
No Result
View All Result
SoftPower News
No Result
View All Result
Home News

Karuma Hydropower May not Meet June Deadline- Auditor General

Ugandan taxpayers are likely to lose even more money on electricity on top of the Shs 100 billion lost last year as the completion and commissioning of the 600MW hydropower station by June 2022 is highly unlikely, the Auditor General has said.

by Muhamadi Byemboijana
February 8, 2022
Karuma Hydropower May not Meet June Deadline- Auditor General
6
VIEWS

Ugandan taxpayers are likely to lose even more money on electricity on top of the Shs 100 billion lost last year as the completion and commissioning of the 600MW hydropower station by June 2022 is highly unlikely, the Auditor General has said.

In his annual report to parliament, the AG says several related programs of the dam are far from being concluded. These include substations in different parts of the country as well as transmission lines that are supposed to evacuate the electricity from Karuma to these stations.

Related Stories

Otafiire to Hand Over Pan-African Movement Chairmanship After 31 Years

Uganda Courts Mauritian Travellers at Inaugural Tourism Roadshow

URSB Scraps Gazette Requirement for Copyright Registration

The dilemma, however, is that should the power station be complete and commissioned before the transmission infrastructure, power produced and not used, also known as deemed energy, will have to be paid for by the government.

The dam, which will be Uganda’s biggest so far, will be three-and-a-half years late than the original date set for its completion.

The delay to complete construction was mainly due to unfinished works such as spillway rehabilitation and other minor defects.

According to the AG’s report for the financial year ended June 2021, the country paid over Shs 87.7 billion for energy produced by independent power producers.

This was in regard to 13 power purchase agreements, which were financed through the electricity tariff system, hence negatively impacting the electricity price to the final consumer. Only one hydro power plant did not fall in this category.

According to several power purchase agreements and other implementation agreements between the power producers, the government and the Uganda Electricity Transmission Co Ltd (UETCL), the government committed to construct power evacuation infrastructure from the generation facilities to the distribution network upon commencement of generation and dispatch of power by IPPs.

“I noted that UETCL continues to pay significant amounts relating to deemed energy purchases. These are significant losses for which the company did not generate economic value. Payment of this amount would significantly affect the company’s cash flows,” says the Auditor General.

Recently, the minister for Energy and Mineral Development, Ruth Nankabirwa said the government had completed the construction of the 248km 400Kv Karuma-Kawanda high voltage line, as well as the 54km 132Kv line from Karuma to Olwiyo in Nwoya and to Lira.

“I noted that the completion of land acquisition process or the Resettlement Action Plan (RAP) for the 132kV Karuma-Lira Transmission Line and Karuma Dam Reservoir by UTECL and MEMD, respectively, remain outstanding,” says the AG’s report.

These when not completed, will affect the commissioning of the Karuma dam, which is also a breach of the employer’s obligations under the engineering, procurement and construction contract with significant risk to the overall project completion.

“I advised the accounting officer to continue engaging the regulator and other sector players to address the infrastructural constraints in the transmission network to ensure efficient evacuation of generated power.” By December last year, construction works for the three substations was at 98%, 90% and 95% respectively.

Nankabirwa said apart from programs to help increase domestic consumption, there are plans to directly transmit electricity to industrial parks, with the Kapeeka project complete.

“To facilitate the supply of power to industrial parks, construction of the Kawanda-Kapeeka power line and Kapeeka substation have been completed to supply power to Kapeeka Industrial Park,” said Nankabirwa.

According to the Energy ministry, by the end of the year, Uganda will have a production capacity of 2000MW from the current 1,250MW however, the amount of unused power will most likely increase due to less demand. But apart from the deemed energy, another Shs 15.3 billion was lost in the evacuation process, according to the AG’s report.

“The amount is due to power evacuation losses stemming from the absence of transmission lines to evacuate electricity from PA Technical, Siti 1 and Arpe Power Plants which resulted in wheeling power over a lower capacity and weaker distribution lines operated by UEDCL.”

The delays are also likely to result in increased supervision costs and increased commitment fees payable on undrawn balances of the loan, of which the government had already paid commitment fees amounting to Shs 2.9 billion as of June 30, 2021.

It also reduces the period between commissioning, commercialization and payback which may influence the electricity tariff structure.

“I advised the accounting officer to ensure that the rectification of pending works under the Karuma dam is expedited to enable project completion and commissioning without further delay,” the auditor general concludes. URN

Tags: Attorney GeneralAuditor GeneralHydropowerKarumaKaruma DamSoftPowerNewstopnewsUganda

Recent Stories

Kaziimba: Appointment of New Canterbury Archbishop Deepens Anglican Rift

Otafiire to Hand Over Pan-African Movement Chairmanship After 31 Years

CPA Ben Patrick Kagoro Honoured with ICPAU Gold Service Award

Gloria Tuhaise Wakooba Named CPA of the Year 2025

Uganda Courts Mauritian Travellers at Inaugural Tourism Roadshow

UPC’s Ogwal Backs Museveni in Kwania Amid Calls for Development

SoftPower News Logo

SoftPower News is a subsidiary of SoftPower Communications LLC, a Ugandan digital media group. Keep posted of the latest from Uganda and East Africa.
Plot 4B Malcolm X, Kololo
P.O Box 1497, Kampala - Uganda
Tel: +256-392-001-701
Email: info@softpower.ug

This news site is licenced by Uganda Communications Commission (UCC)

ADVERTISEMENT
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
  • Regional
  • Defence & Security
  • Sport
  • Entertainment
  • More

© SoftPower News

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Add New Playlist

error: Content is protected
No Result
View All Result
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
    • Fashion
  • Regional
    • Kenya
    • Rwanda
    • Tanzania
    • Burundi
    • South Sudan
    • DR Congo
  • Defence & Security
  • Sport
  • Entertainment
  • More
    • Agriculture
    • Africa
    • Columnists
    • Education
    • Health
      • COVID-19
    • International News
    • News in Pictures
    • OpEd
    • Pearl Of Africa
    • People
    • Politics
    • Special Reports
    • Women

© SoftPower News

Are you sure want to unlock this post?
Unlock left : 0
Are you sure want to cancel subscription?