• Latest
Gov’t loses Shs150m Daily to Compensation Delays on Kampala Northern Bypass

Gov’t loses Shs150m Daily to Compensation Delays on Kampala Northern Bypass

9 years ago
Museveni, Ruto Break Ground for Kisumu – Malaba SGR

Museveni, Ruto Break Ground for Kisumu – Malaba SGR

16 hours ago
NFA, Rotary and UBL Launch Tree Restoration Project in Namananga Forest

NFA, Rotary and UBL Launch Tree Restoration Project in Namananga Forest

23 hours ago
Stanbic Bank Launches “Kikole Ku Speedii” to Accelerate Digital Banking

Stanbic Bank Launches “Kikole Ku Speedii” to Accelerate Digital Banking

1 day ago
DJ Dash to Turn Up Mezo Noir’s Useless Mondays with ‘The Dash Affair’

DJ Dash to Turn Up Mezo Noir’s Useless Mondays with ‘The Dash Affair’

1 day ago
Baileys Brings Ultimate Adult Indulgence to Old School RnB Picnic

Baileys Brings Ultimate Adult Indulgence to Old School RnB Picnic

2 days ago
Mungu Feni Calls For Unity in West Nile as  Al Sham Medical Center Wins Eid Tournament in Arua

Mungu Feni Calls For Unity in West Nile as Al Sham Medical Center Wins Eid Tournament in Arua

2 days ago
SoftPower News
Sunday, March 22, 2026
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
    • Fashion
  • Regional
    • Kenya
    • Rwanda
    • Tanzania
    • Burundi
    • South Sudan
    • DR Congo
  • Defence & Security
  • Sport
  • Entertainment
  • More
    • Agriculture
    • Africa
    • Columnists
    • Education
    • Health
      • COVID-19
    • International News
    • News in Pictures
    • OpEd
    • Pearl Of Africa
    • People
    • Politics
    • Special Reports
    • Women
No Result
View All Result
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
    • Fashion
  • Regional
    • Kenya
    • Rwanda
    • Tanzania
    • Burundi
    • South Sudan
    • DR Congo
  • Defence & Security
  • Sport
  • Entertainment
  • More
    • Agriculture
    • Africa
    • Columnists
    • Education
    • Health
      • COVID-19
    • International News
    • News in Pictures
    • OpEd
    • Pearl Of Africa
    • People
    • Politics
    • Special Reports
    • Women
No Result
View All Result
SoftPower News
No Result
View All Result
Home News

Gov’t loses Shs150m Daily to Compensation Delays on Kampala Northern Bypass

by SoftPower
September 7, 2017
Gov’t loses Shs150m Daily to Compensation Delays on Kampala Northern Bypass
8
VIEWS

Uganda National Roads Authority (UNRA) Director Land Acquisition, William Matovu has appealed to politicians and leaders in the Central region to help with the delays on road constructions that are caused by huge compensation claims.

Matovu made the call during a one day engagement of stakeholders from central region on the progress of the multi-lane project aimed at decongesting the city centre.

Related Stories

Museveni, Ruto Break Ground for Kisumu – Malaba SGR

NFA, Rotary and UBL Launch Tree Restoration Project in Namananga Forest

Stanbic Bank Launches “Kikole Ku Speedii” to Accelerate Digital Banking

Matovu said that government loses a lot of money due to the delays caused in negotiating compensations which sometimes fail to yield results.

The director revealed a case the reason which government is currently losing Shs150m daily to the contractor of Kampala Northern Bypass Highway due to delays caused by huge compensation claims put across by the landlady at a section around Namungona roundabout.

According to Matovu, the contractor MOTA-ENGIL, Engenharia E Construcao SA, a Portuguese construction company demobilized machinery from the section until he gains access to the land which is costing government lots of funds.

“Government is losing approximately Shs150m everyday. We have engaged the landlady for two months now and have so far failed to reach an agreement; the affected portion of land is very small, the building is intact, only the perimeter wall and gate were affected,” Matovu said.

Matovu said that, “The affected structures were valued at Shs60m which she accepted in the first place but later rejected it demanding a compensation of Ssh398m.”

He added that such compensation delays have affected several road projects urging leaders to always speak to land owners to allow free passage of road projects.

Recent Stories

Museveni, Ruto Break Ground for Kisumu – Malaba SGR

NFA, Rotary and UBL Launch Tree Restoration Project in Namananga Forest

Stanbic Bank Launches “Kikole Ku Speedii” to Accelerate Digital Banking

DJ Dash to Turn Up Mezo Noir’s Useless Mondays with ‘The Dash Affair’

Baileys Brings Ultimate Adult Indulgence to Old School RnB Picnic

Mungu Feni Calls For Unity in West Nile as Al Sham Medical Center Wins Eid Tournament in Arua

SoftPower News Logo

SoftPower News is a subsidiary of SoftPower Communications LLC, a Ugandan digital media group. Keep posted of the latest from Uganda and East Africa.
Plot 4B Malcolm X, Kololo
P.O Box 1497, Kampala - Uganda
Tel: +256-392-001-701
Email: info@softpower.ug

This news site is licenced by Uganda Communications Commission (UCC)

ADVERTISEMENT
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
  • Regional
  • Defence & Security
  • Sport
  • Entertainment
  • More

© SoftPower News

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Add New Playlist

error: Content is protected
No Result
View All Result
  • News
  • Tourism & Travel
  • Business
  • Lifestyle
    • Fashion
  • Regional
    • Kenya
    • Rwanda
    • Tanzania
    • Burundi
    • South Sudan
    • DR Congo
  • Defence & Security
  • Sport
  • Entertainment
  • More
    • Agriculture
    • Africa
    • Columnists
    • Education
    • Health
      • COVID-19
    • International News
    • News in Pictures
    • OpEd
    • Pearl Of Africa
    • People
    • Politics
    • Special Reports
    • Women

© SoftPower News

Are you sure want to unlock this post?
Unlock left : 0
Are you sure want to cancel subscription?